Drainage beneath a new concrete slab needs its route, levels and outlet positions settled before concrete covers it. Send the foundation plan, drainage drawings and proposed fixture layout first, along with your builder’s intended pour sequence.

- PGDB licensed
- Site Safe member
- Impac Prequal assessed
- Kiwi-owned since 2012
How it works
Call or enquire
Phone us or send the address and what you’re seeing.
We assess
A licensed Stately plumber looks at the job on site.
Clear quote
You get a plain explanation and a clear quote before work starts.
Job done and tidied
We finish the work and leave the site clean.
Stately covers Half Moon Bay. We use the plans and an onsite check to establish the drainage work and coordinate the excavation, pipe laying and testing with slab preparation.
Fix the drainage positions before digging
Send the latest drawing revisions, not just the kitchen or bathroom sketch. Include finished floor levels, footing details and the locations of toilets, showers and other fixtures needing drainage through the slab. Mark any unresolved layout choices. A moved toilet can change a buried junction, so agree those positions before setting out the trenches.
We compare the proposed outlets with the building setout and available connection level onsite. The designer resolves conflicts between pipe routes, foundations and structural details. Confirm the drainage consent requirements for the actual work using MBIE guidance, then put any required inspection stages into the builder’s programme before booking concrete.
Locate the outlet and open the trenches
Supply any existing drainage plans and information about buried services. We locate the intended receiving drain and check its position, depth and condition where the new work will join. A line drawn on an old plan is a starting point; exposed connection details give us the levels needed for the job.
Excavation follows the agreed route, with room to prepare bedding and make joints properly. Keep spoil and machinery access coordinated with the foundation crew. Where digging or construction approaches public wastewater pipes, check Watercare’s approval requirements before excavation. Keep that decision ahead of the pour programme, rather than discovering an approval issue beside an open trench.
More about drainlayer in Half Moon Bay
Lay pipework around the foundation sequence
We prepare the trench base and lay the specified drainage pipework at the checked levels. Junctions, bends and risers follow the agreed layout. Pipe support matters throughout the run, including beneath joints and where drainage passes through the slab. Foundation penetrations and clearances are coordinated with the designer’s details before surrounding work closes them in.
We repair or replace the agreed section of existing drainage where the connection requires it. Open pipe ends are capped against concrete and debris. Restricted drainlaying belongs with an appropriately authorised person; use the PGDB register to check the person undertaking it. Give the builder clear riser positions to protect during reinforcing and slab preparation.
Hold the pour until checks are complete
Testing comes while the pipework remains accessible for checking and correction. We check the laid route, levels, joints and outlet positions against the drawings, and complete the testing required for the work. Arrange required inspections at the appropriate stage. Do not bury an inspection point beneath fill or reinforcing before the relevant check is completed.
For a new wastewater connection, include Watercare’s application, inspection and completion steps in the programme. Keep that connection process separate from the concrete booking. Once testing and inspection requirements are satisfied, coordinate backfilling and compaction with the slab team. Recheck exposed risers for movement or damage before concrete placement.
Hand over buried drainage with usable records
Record the installed route, junctions and connection location before covering them. Keep measurements tied to identifiable building points, together with photographs, test records and applicable inspection documents. Give the owner and builder the drainage layout, including agreed changes, so later alterations start with a useful record of what lies below concrete.
At handover, identify which trenches have been backfilled and which areas remain for the builder’s slab preparation or surface reinstatement. Leave pipe openings protected and access points identifiable. Explain any outstanding drainage connection work and who coordinates it, so the owner understands what is complete before the floor hides the installation.
Drainlayer: questions from Half Moon Bay
Can we move a shower after drainage is laid?
Raise the change before backfilling. We check the revised position onsite with the drawings. Altered pipework needs its checks completed before the slab proceeds.
What if the existing outlet is too shallow?
The measured outlet level goes back to the designer for a workable drainage arrangement. Resolve that arrangement before fixing slab penetrations or continuing the affected trench.
Who protects the pipes during the pour?
Agree responsibility with the builder before concrete arrives. Mark risers clearly, keep caps fitted and check exposed pipework after surrounding trades finish their preparation.
More help in East Auckland
Read before you call
Google reviews
Rated Excellent
Real words from Auckland customers on Google.
Actually awesome and the reviews are correct… on time, job well done and sorry about the bad replacement tap I provided you.
5 / 5